Yellowstone project

Manager: Tony
Start: April 1, 2007
Finish: June 14, 2007
Report Date: April 8, 2007

Gantt Chart

WBS Name Work Week 15, 2007 Week 16, 2007 Week 17, 2007 Week 18, 2007 Week 19, 2007 Week 20, 2007 Week 21, 2007 Week 22, 2007 Week 23, 2007 Week 24, 2007
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 Tony - website graphs/data collection 45d
2 Tony - Google maps/front end 45d
3 David - 2nd BS done 45d
4 David - complete 2 or more 900mhz radios 45d 1h
5 David - focus on long range radio integration 42d 3h
6 Tony - error handling 41d 7h
7 Matt - Long range radio finished 150d 1h
8 All - New LR radio software development 21d 2h
9 All - Test and debug new LR radio software 20d 7h
10 Test new setup in the Santa Cruz Wilderness 20d 7h
11 Tony - work on routing through nodes 41d 7h

Tasks

WBS Name Start Finish Work Priority Complete Cost
1 Tony - website graphs/data collection Apr 1 Apr 16 45d 0%
2 Tony - Google maps/front end Apr 16 May 1 45d 0%
3 David - 2nd BS done Apr 1 Apr 16 45d 0%
4 David - complete 2 or more 900mhz radios Apr 16 May 1 45d 1h 0%
5 David - focus on long range radio integration Apr 30 May 14 42d 3h 0%
6 Tony - error handling Apr 30 May 13 41d 7h 0%
7 Matt - Long range radio finished Apr 1 May 21 150d 1h 0%
8 All - New LR radio software development May 21 May 28 21d 2h 0%
9 All - Test and debug new LR radio software May 28 Jun 3 20d 7h 0%
10 Test new setup in the Santa Cruz Wilderness Jun 4 Jun 10 20d 7h 0%
11 Tony - work on routing through nodes Jun 1 Jun 14 41d 7h 0%

Resources

Name Short name Type Group Email Cost